1601 Mariposa Update

Workers will be digging trenches for building footings between 2/12/18 and 4/30/18. This will generate approximately 3000 cubic yards of lead-contaminated soil, with approximately 150 trucks entering and exiting the site on 18th Street to off-haul the soil.

Required safety measures include:
• Controlling dust by spraying water on exposed soil
• Cleaning trucks and wheels of soil and mud before leaving site
• Following specific transportation routes
• Stopping excavation when it's windy
• Washing streets and sidewalks regularly

Note that you always can contact Nick Vanderboom, Senior VP of Related (phone: 415-653-3162 / 213-300-1786, email: NVanderboom@Related.com) and/or Tom Lanphar from DTSC (phone: 510-540-3776, email:  tom.Lanphar@dtsc.ca.gov)  with any immediate concerns.

Draft EIR has been issues and public hearing scheduled!

Important Dates for 1601 Mariposa Project

  • December 17 - The Draft EIR for the proposed development has been issued. The report can be viewed online here
     
  • December 17- February 17 - Comment period for the Draft EIR. Written comments can be sent to the Environmental Review Officer, Sarah Jones:
  • January 22 - The public hearing on the Draft EIR will be held at the Planning Commission. The purpose of the hearing is to receive testimony related to the accuracy and completeness of the Draft EIR. Please save this date and plan to attend. Later in the year, the Planning Commission will be voting on whether to approve the EIR. A large turnout at the January 22nd hearing is imperative and will demonstrate our deep concerns with the impacts of the project. 

Grow Potrero Responsibly's Next Steps


The Draft EIR is very extensive. GPR will be taking the next few weeks to review the report and we will contact you via email with our opinions.  Please check our website for the most current information.