1601 Mariposa Project Schedule

May 2018 – Foundation establishments, underground plumbing, and formation of concrete walls, columns and elevated decks. Erection of crane near Carolina Street and Mariposa Street. Vertical wood framing construction on Carolina Street. Parking will be limited during concrete pours and during site deliveries.

June 2018 – Foundation establishments, underground plumbing, and formation of concrete walls, columns and elevated decks. Erection of crane near Arkansas Street and 18th Street. Vertical wood framing and metal framing construction on Carolina Street and Arkansas Street. Parking will be limited during concrete pours and during site deliveries.

July 2018 – Formation of concrete columns and elevated decks. Vertical wood framing and metal framing construction on Carolina Street and Arkansas Street. Parking will be limited during concrete pours and during site deliveries.